Answers to Association
Questions Concerning
Westgate Blvd\Davis Lane Improvements
The following questions were submitted in February 2008 by Dominic Chavez,
President of the Castlewood-Oak Valley Neighborhood Association, on behalf
of the neighborhood associations in the Davis/West Gate area. Responses
from Public Works Transportation engineers are inserted following each
question.
1. What design features could be considered for Westgate to reduce cut-through
speeds and pedestrian/car interaction, particularly for the portion south
of Davis Lane? For example, what about four-way stops at Cohaba/Westgate
and Nesbit/Westgate? Crosswalks?
West Gate is designated as an arterial
street in the City’s roadway plan. Therefore, its function
is to carry through traffic. Construction of the missing section
could provide relief to some area residential and residential collector
streets that may currently have cut-through traffic as people try
to find their way between Cameron Loop and Slaughter. Arterial streets
are not eligible for traffic calming devices. However, speed limit
signs will be installed to advise drivers of the legal speed.
Pedestrian and bicyclist accommodations would
be provided by the construction of sidewalks and bike lanes. If
constructed as a 4-lane divided section, sidewalks and bicycle lanes
would be provided on both sides of the roadway. However, if an undivided
roadway is constructed, a sidewalk would be constructed on only
one side of the roadway now. The other sidewalk would be constructed
as part of the future expansion to a 4-lane divided roadway. Initial
construction as an undivided section would include width for a bicycle
lane. However, the bicycle lane would not be marked until the future
expansion to a 4-lane divided roadway provided the bicycle lane
for the opposite direction.
Stop signs are used to indicate which drivers
must always come to a complete stop. An all-way stop should not
be installed at an intersection unless there are specific conditions
that can be successfully addressed by the stop signs. Any all-way
stop installations would be subject to meeting the criteria listed
in the Texas MUTCD. Typically, crash history and/or entering traffic
volumes are the basis for such installations. The Texas MUTCD lists
crash history justification based on five or more crashes within
a 12 month period that are susceptible to correction by an all-way
stop and entering traffic volume justification based on at least
300 vehicles per hour for 8 hours of the day on the major street
and at least 200 vehicles, bicyclists, and pedestrians per hour
for the same 8 hours of the day on the minor street. Roadway construction
would have to be complete and the roadway open to traffic in order
to collect the needed traffic volume data.
The installation of marked crosswalks would
be based on demonstrated pedestrian activity. Due to the presence
of Cowan Elementary School, crosswalks at Davis and Cohoba may be
appropriate if there are students crossing West Gate walking to
or from school. For elementary school age pedestrian crossings,
we would install a reduced school speed zone in addition to a crosswalk.
Criteria listed in the City’s School Safety Manual for the
installation of a reduced school speed zone include pedestrian volumes
(40 or more in a 2 hour period or 20 or more in 1 hour) and vehicular
volumes (200 or more per hour at the same times as the pedestrian
volumes).
|
2. If Westgate is extended (in full or part), can we be guaranteed traffic
calming along some neighborhood north/south roadways that parallel Westgate
(i.e. Curlew)
| The Neighborhood Traffic Calming Program (NTCP)
is completely independent of roadway construction projects. Funding
for this program is included in the City’s annual budget this
year for the first time in several years. One of the neighborhoods
selected for this program this year includes the area on both sides
of West Gate between Slaughter and Davis. Traffic calming on specific
streets is subject to meeting certain minimum volume and speed criteria,
being included in the recommended plan by the neighborhood working
group, and a successful vote of the area residents and owners. The
NTCP process is underway in this area. The first meeting was February
7. Volunteers for a working group to guide the development of the
traffic calming plan were solicited at this meeting. |
3. What funds, if any, have been provided by the Grand Oaks Subdivision
developer at Davis/Manchaca to improve that intersection?
| Based on information we requested when the
Davis/ West Gate options were being prepared, the Grand Oaks Subdivision
posted $215,250. $161,700 of this was for the full width of the street
and $53,550 was for drainage collection system. The amount of developer
participation is determined based on the impact of their site. Participation
for individual projects is generally insufficient to permit roadway
improvements until combined with additional funds. |
4. Is there adequate right-of-way along Davis Lane at Manchaca to develop
a dedicated left-turn bay that would alleviate the single-lane stacking
that occurs currently? What would be the cost to fund such an improvement?
Due to the distance between the Manchaca
intersection and the Express/Escabosa intersection, any improvements
for traffic approaching Manchaca may need to extend to west of Express/Escabosa.
Otherwise, there would be a relatively short 2-lane section of roadway
between two wider sections. Pavement width transitions in such limited
distances can present problems for road users – especially
in wet or dark conditions.
Based on information in the City GIS data,
it appears there may be some areas where additional right-of-way
would be needed. A cost estimate for improvements from Manchaca
to west of Express/Escabosa is included as the last item in #12.
|
5. Will improvements on Davis Lane east of Leo Street result in the infringement
or elimination of the hike/bike trail developed by the Grand Oaks Subdivision?
| If the existing trail is outside the right-of-way
and no additional right-of-way is needed, the trail will not be eliminated.
Specific right-of-way limits, roadway cross sections and roadway placement
within the right-of-way would be addressed in the design stage. This
level of detail would not be performed until the project was funded. |
6. Davis Lane from Zeke Bend to its current terminus is four-lane divided.
How will the new connection between this section to Leo Street transition
to the existing two-lane undivided or one of the proposed improvement
options available for Davis Lane east of Leo Street under consideration?
Construction of the missing section of
Davis Lane between Leo Street and the dead-end east of Huebinger
Pass is a funded project. The transitions to the adjacent pavement
widths on each end of this project will be included as part of that
work. The west end will have a tapered width reduction from the
wider existing cross section to the new two-lane section. The width
transition on the east end will occur east of Leo Street. The existing
pavement will be widened for about 500 feet to include a westbound
left turn lane and to match the overall width of the new construction
west of Leo. The work on Davis east of Leo is not considered an
improvement project for that roadway section.
Only one of the options presented at the
October 16 meeting, Option 7, included construction that would adjoin
the section of Davis immediately west of Zeke Bend. Specific design
details have not been determined at this point. However, if Option
7 is chosen for construction, a transition from the wider existing
4-lane divided cross section to the new cross section at West Gate
will be included in the design.
The existing divided section of Davis Lane
east of Zeke Bend will be marked for a single through travel lane
and a bicycle lane in each direction.
|
7. Will the intersection of Westgate at Davis Lane have a signalized
intersection under all scenarios where Westgate is improved?
| Traffic signal installation would not be assumed
or automatically included in any of the construction options. Any
signal installation would be based on the warrants listed in the Texas
MUTCD. Studies to determine if any of these warrants are satisfied
would be performed after construction was completed and the new roadway
sections opened to traffic. |
8. If all or part of the Westgate extension is constructed, what (if
any) improvements will be made to Davis Lane on either side of the intersection?
Will there be dedicated turn lanes constructed on Davis to facilitate
turn movements both north and south, and eliminate potential stacking
along Davis?
| There are too many possible option combinations
under consideration at this point to say definitively. However, preliminary
designs for the initial recommended West Gate construction included
widening Davis and including left turn lanes for a short distance
each side of West Gate. |
9. What improvements are currently funded or being developed to improve
the intersection at Davis Lane and Brodie Lane where development is currently
occurring on the Southeast corner, and set to begin on the Northeast corner?
How much money (and for what improvements) were the landowners/developers
of these parcels (as well as the KB condo development that fronts Brodie
Lane and Davis Lane) required to provide the city and is it available
to improve the intersection and/or portions of Davis Lane? How are these
funds/improvements (if they exist) factor into the bond funding and various
scenarios under consideration for improving Davis Lane?
|
Construction and realignment of Davis Lane
from Corran Ferry Drive to Brodie Lane is a funded project. It includes
widening part of the existing roadway to a 4-lane divided roadway
and constructing a 4-lane divided roadway on a new alignment to
intersect Brodie across from the existing portion of Davis Lane.
This project will include widening Davis a short distance east of
Brodie to provide one eastbound departure lane, one westbound left
turn lane, and a westbound combination through/right turn lane.
Two of the options presented at the October
16 meeting, Options 8 and 9, would provide for reconstruction of
Davis east of Brodie. Unless one of these projects is funded, no
improvements to Davis east of Brodie are planned at this time other
than the intersection modifications noted above.
We requested fiscal information for the items
you inquired about from the Watershed Protection Development Review
Department. In addition to the $215,250 noted previously for the
Grand Oaks Subdivision, the following has been posted:
$35,495.00 for the WW Brodie Subdivision
(C8-01-0265.0A) on the northeast corner of Brodie at Davis.
$32,603 of this amount is for street construction and $1,892
is for E/S controls.
$417,498 for the Harris Ranch subdivision (C8-05-0036.0A)
along the south side of Davis for the entire extent between
Brodie and future West Gate. This includes $185,060 for street
construction, $146,138 for drainage collection system, $30,300
for erosion controls, and $56,000 for sidewalks.
|
These funds can be used for improvements
to Davis Lane between Brodie and West Gate that are adjacent to
the developments that posted the funds. If the roadway improvements
do not include the entire length of the development, the funds used
for the roadway improvements must be prorated based on the length
of improvements adjacent to the development..
There is also $13,125 posted for the Harris
Ranch subdivision (C14-03-0157) based on a Traffic Impact Analysis
for a pro-rated share of turn lanes as follows:
Westbound right turn lane on Slaughter
at Brodie - $788
Northbound & southbound left turn lanes on Brodie at Slaughter
- $1,880
Westbound right turn lane on Davis at Brodie - $6,353
Northbound right turn lane on Brodie at Davis - $1,437
Eastbound right turn lane on Davis at Manchaca - $2,667 |
Any available developer funding is applied
to the roadway construction costs as projects are constructed. Such
funds are used to supplement available City funding. Depending on
the circumstances, this may either reduce the amount of City funds
required to complete the project or it may permit more construction
than would be possible with City funds alone.
|
10. What are the approved zoning for the following parcels:
• Parcels of land to be bisected by Westgate to immediate north
of Davis Lane (both west and east parcel)
• Parcel of land between Davis and Kentish just north of Cowan campus
The Development Assistance Center provided
the following zoning information:
North of Davis Lane, the property on either
side of the West Gate ROW is zoned LR-CO – Neighborhood Commercial
– Conditional Overlay for the tracts south of the pipeline
easement, and MF-2-CO – Multi-family Residence (low density)
– Conditional Overlay, for the portions north of the pipeline.
For those parcels, the conditional overlay prohibits any development
until the construction of West Gate Blvd. is completed from Cameron
Loop to Davis Lane.
The property between Cowan Elementary and
Davis Lane is currently zoned RR – Rural Residence zoning.
|
11. What obligation does developer/landowner(s) at intersection of Westgate
and Davis have related to funding improvements at this intersection?
| Generally, a developer can be required to
fund and/or construct a 2-lane roadway needed for site access in conjunction
with their development. The City can not require developers to fund
or construct multi-lane divided roadways. |
12. What would be the cost to fund the following and what sources could
be utilized (i.e. developer participation, bonds, etc):
As background information, $8,580,000 is
the estimated cost to construct the entire missing section of West
Gate as a 4-lane divided roadway. This is the assumed amount available
in consideration of other construction options. Any available developer
participation would be in addition to this amount.
A. Westgate (Cohoba to Davis)—4 lane
divided with dedicated turn bays on Davis Lane at intersection of
Davis/Westgate (left turn bay on westbound Davis, right turn bay
on eastbound Davis);
This is basically the combination of Options
3 and 7 from the October 16 meeting except that Option 7 does not
include a separate right turn lane for Davis at West Gate. The estimated
combined cost for Options 3 and 7 is $5,659,650. This would leave
$2,920,350 available.
Right turn lanes would not typically be included
for turns from Davis to West Gate. Construction of right turn lanes
would have to be subject a determination that the turning volumes
justified the separate lane, that any needed right-of-way either
exists or can be acquired, and that sufficient funding exists.
B. Dedicated right turn bay at intersection
of Davis and Brodie Lane that could maximize cueing and separate
traffic moving northbound and southbound on Brodie (or going straight
assuming the realignment of Deer/Davis Lane on west side of Brodie);
This question has been interpreted as addressing
lanes on Davis with traffic wishing to turn to travel northbound
or southbound on Brodie. No construction is anticipated on Brodie
as part of this process.
The Davis project from Brodie to Corran Ferry
currently under design will include construction of an eastbound
left turn lane plus two additional eastbound approach lanes at Brodie.
Since Davis east of Brodie has and will continue to have only one
departure lane, one of the two additional eastbound approach lanes
will be marked for right turns only. Therefore, while no additional
right-of-way or pavement will be needed, it will be possible to
have a dedicated right turn lane for eastbound traffic on Davis
approaching Brodie.
The Davis project from Brodie to Corran Ferry
will include widening of Davis immediately east of Brodie to provide
a westbound left turn lane and to provide proper lane alignment
through the intersection. However, this widening does not include
a separate westbound right turn lane.
A separate right turn lane for westbound
Davis to Brodie was not included in the cost estimates for Options
8 or 9. Such a lane could be considered if demand, right-of-way,
and funding issues are successfully addressed. We do not have a
cost estimate for such a lane.
C. Dedicated right turn bay at intersection
of Manchaca and Davis that could maximize cueing and separate traffic
moving northbound and southbound on Manchaca;
This question has been interpreted as addressing
lanes for eastbound Davis approaching Manchaca. Dittmar on the east
side of Manchaca currently has separate left turn, straight and
right turn lanes. Manchaca also has existing lanes designated for
right turns only for both southbound and northbound traffic.
Construction of just a right turn lane on
Davis approaching Manchaca is not anticipated in this process. However,
if a project providing an overall roadway capacity improvement is
chosen, it is likely that at least two eastbound Davis approach
lanes would be provided at Manchaca for a longer distance than the
current roadway. See related information provided in response to
#12D below to item #4.
D. Davis Lane from Manchaca to Express Blvd—2
lane with center turn lane
This is a portion of Option 10 presented
at the October meeting. The cost estimates for Options 10 and 11
were based on a per linear foot unit cost. This overall section
is approximately 3,200 feet long. The section from Manchaca to include
an eastbound left turn lane to Express is approximately 1,500 feet.
Using a proportional cost calculation, the estimated cost from Manchaca
to west of Express would be $2,679.609.
|
13. When construction begins, will it be phased to reduce traffic and
access issues to the greatest extent possible?
| Construction phasing tries to avoid unacceptable
inconvenience to the traveling public while permitting the contractor
to work in logical segments. Construction phasing is often dictated
by the location and cross section of the existing roadway and its
relation to the planned roadway. Existing or planned underground utilities
also dictate some phasing decisions. From the contractor’s standpoint,
closing the construction area to all traffic provides the greatest
ease of construction. From the road user’s standpoint, no or
minimal lane closures is best. Projects seldom proceed at either of
these extremes. Roadway construction phasing is a challenging balance
between efficiency and convenience. Phasing that would keep traffic
disruptions to an absolute minimum would be prohibitively expensive
and would often significantly extend the time required to complete
the project. Therefore, while traffic and access issues are considered,
inconvenience to both the road users and contractor can be expected. |
|